Wednesday, December 10, 2008

Roof on

On Monday the roofers started on our extension for Nursery & Kids Church. By Monday evening all the felt and batons were fixed and by Tuesday night 95% of the tiles were laid. Today they are getting on with the more awkward pieces but hopefully they should be finished today.

That meant the new extension should start drying out from all the downpours we have had over the last few weeks.

We are still on track for a completion in mid to late February.


0 comments:

Post a Comment